CISG
SLOVAKIA

Article 75sk en

<< Article 74 <<                               List of Articles                                >> Article 76 >>


Article 75
[slovenske znenie]


If the contract is avoided and if, in a reasonable manner and within a reasonable time after avoidance, the buyer has bought goods in replacement or the seller has resold the goods, the party claiming damages may recover the difference between the contract price and the price in the substitute transaction as well as any further damages recoverable under article 74.

 

 

 

CASE LAW:

 

 

 

CISG ADVISORY COUNCIL OPINIONS:


CISG AC OPINION 8: Calculation of Damages under CISG Articles 75 and 76 

 

 

LITERATURE:

 

 

 

 

see also annotated Article 75 in Pace Database


see also case law to article 75 in the UNCITRAL Digest of case law 

 

 

left pannel book